2024 Brictec - Malaysia CBT Decorative Bricks Production Line Project
Date:2024-12-11
一、Project overview
Malaysia CBT decorative bricks production line project is Brictec's flagship model project in Southeast Asia, designed to produce a daily output of 70,000 decorative bricks (215x100x67mm). Due to the molding shift of 6 days per week, the actual daily output is about 85,000 pieces.
The main project process for decorative bricks production line:
The project adopts wet plastic extrusion process, its drying adopts single layer tunnel dryer with support bar recycling, and firing uses external firing tunnel kiln with flat ceiling of lightweight mullite. The operating equipment can be automatically controlled, and the drying chamber and tunnel kiln are centrally controlled.
November Project Phase Summary
1.Drying Chamber Section
1:The cyclone base and main shaft motor on the top of the drying chamber have been installed,22 cyclone cone barrels have been installed and debugged,and 65 fans have been installed;
2:The hot air pipe was produced on November 25,and the welding and assembly were completed;
3:The concrete pouring of 2 out of 4 lines of the internal track of the drying chamber has been completed,and the other 2 lines are expected to be completed before December 8;
4:The ferry lane construction at the vehicle exit has been completed;
5:The hot air feeding blowers have been moved to the installation location;
6:65 cyclone column piers have been poured.
2.Tunnel Kiln Section
1:After the completion of the ceiling beams,85 beams have been installed,along with 1512 secondary beams;
2:The concrete pouring for the tunnel kiln ring beam has been finished;
3:The construction of 2 return lines in the pre-drying chamber has been completed;
4:The foundation construction of the ferry lane at the exit has been completed,and the steel bars of the track beam have been tied,awaiting track installation;
5:The concrete pouring of the moisture exhaust chamber at the entry has been completed, and the case-in-place concrete top plate at the exit has also been completed;
6:The ground of the return line has been excavated,and the crusher will be brought in next week to crush the ground,after which construction will commence;
7:3780 lightweight high-aluminum hanging bricks and 3780 MG-26 polylight mullite ceiling bricks have been bonded.
3.Process Equipment Foundation Section
Excavation of box feeder foundation and positioning of super fine roller mill.
4.Arrival Status
The second batch of domestic goods 2-4,2-5,and 2-6,total 15 containers arrived at the site,the inventory was completed without any damage or quantity error,the goods were placed in an orderly manner in the designated location of the workshop.
5.On-Site Documentary Pictures