GPH ECO CERAMICS 2019-2020
Time:2023-03-22
GPH
ECO CERAMICS
2019-2020
ECO CERAMICS is part of the Bangladesh GPH Group, which is the largest building material manufacturer in Bangladesh. It has the top three cement factories and the largest steel plant in Bangladesh, and the brick factory project currently under construction will also become Bangladeshi domestic The brick factory with the largest volume and the highest degree of industrialization.
The project adopts advanced twice brick setting technology, the drying process adopts automatic upper and lower racks and tunnel-type single-layer drying system, and the burning process adopts two tunnel kilns with a section of 4.8 meters and an automatic pulverized coal combustion system. The entire brick-making production process has a high degree of automation and strong controllability, which can simultaneously meet the needs of producing ordinary bricks and high-end bricks. On March 31, 2019, Xi'an Ruitai & Shandong Mining Machinery Maike Project Department officially settled on the site, and the groundbreaking ceremony was held with Party A to formally take over the construction and management of the entire project.
March 2019-december 2020
will
Delivery to production
Idea
【Customer-centric, striver-oriented】
21 months 630 days
21 months, 630 days, Xi’an BRICTEC is consistent,Do everything carefully, from process design to technical control to the construction site, we are all to ensure that every customer “makes bricks easily”
GPH
CERAMICS
19 batches of personnel exchamges,56 technical engineer support
Project manager:He Feng(Xi’an BRICTEC)
Project translation:Wang Jianqing(COSMEC)
Civil engineer:He Feng(Xi’an BRICTEC)
Electrical engineer:He Feng Sun Jianhua(BRICTEC&COSMEC)
Mechanical engineer:Wang Shouyou(COSMEC)
Furnace engineer:Li Zongning(Xi’an BRICTEC)
Business docking:Chen Yumao(Xi’an BRICTEC)
Process design:Zhao zhouming Su Xiaohui Guo Chaohui(Xi’an BRICTEC)
Procurement services:Li Jiankun Yuan Yongkang(Xi’an BRICTEC)
Supervision unit:Monir Hosain BRICTEC Bangladesh branch
Other personnel:26
5 months150 days
A total of 150 days from February to July 2020, the project was affected by the outbreak.
The most beautiful retrograde
2020
200 containers
200 containers, from delivery to the project site, behind it is a team, but also a belief and responsibility.
Help you to make bricks easily!
90 kiln cars 320 drying cars
BONGIOANNI
MACCHINE
Italy
BONGIOANNI vacuum extruder
DRYING CHAMBER OF TUNNEL TYPE
Xi’an BRICTEC
TUNNEL KILN BURNING SYSTEM FOR PULVERIZED COAL
GPH
CERAMICS