October Brictec–MUSK Project Site Construction Update
Date:2026-10-08
October Brictec–MUSK Project Site Construction Update
I. Project Overview:
The MUSK project is located in Kirkuk, Iraq, and is planned as a modern block production base with a daily output of 800 tons. Its product range covers load-bearing blocks, standard bricks, and partition blocks, meeting the material requirements of various local building structures and providing a stable, high-quality supply for regional urban construction.
II. Construction Update:
Construction activities at the MUSK project site are proceeding efficiently and in an orderly manner. At the current stage, the focus is on the drying chamber, tunnel kiln masonry, and partial construction of the aging warehouse.
Brictec has established a comprehensive on-site construction management system and engineering quality acceptance standards. Throughout construction, all process and inspection standards are strictly implemented. For example, critical procedures such as verticality inspection of formwork for drying chamber frame columns and elevation re-measurement of kiln walls are carried out under standardized process control to ensure construction quality.
III. Site Photos:
Concrete curing of the material storage warehouse retaining wall foundation

Drying Chamber Construction Update:
• Steel bar tying for the second span roof slab of the drying chamber



• Pipe fabrication on the drying chamber roof



• Construction of structural columns for the drying chamber

• Verticality inspection of formwork for the drying chamber's frame columns

Tunnel Kiln Construction Update:
• Storage of insulation cotton for the tunnel kiln

• Elevation measurement of tunnel kiln walls


• Red brick masonry below the curved sealing bricks of the tunnel kiln


Project Name: Brictec–MUSK
Information Source: Brictec Engineering Department
Edited and Published by: Brictec Marketing Department
Release Date: October 8, 2026